Spit Syphon Lid Replacement and Rehabilitation

Client: Pentair
End Client: Sydney Water
Location: The Spit, Manly, Sydney NSW
Date: 2014
Value: $1 million approx..
Duration: 8 Weeks
Project Details:
EYWAD’s works consisted of ancillary ventilation concept design and installation, reinforced steel remediation, epoxy application, grit blasting, installation of temporary hanging work deck, installation of new stainless steel syphon lids.
This was a high risk project, of major concern to Sydney Water, due to the sensitivity of the the location and odour complaints in the past. The Syphon is also notorious for extremely high and dangerous gas levels. The works were executed by Eywad with zero incidents or complaints
from, the public, in live flows.
Want to find out more information?
Please contact us by calling 1300 239 923 or email us at admin@eywad.com